Project Scope:
Receive, store, deliver and set a 60,000-lbs watertube boiler.
For this project, GTI was tasked with the handling of this replacement boiler unit. Unloading the boiler at the entrance to the plant required a 200-ton capacity mobile crane. The unit was then skated through the facility, making a few narrow turns before coming to rest in its final location.